City of Miramar AI Boot Camp · July 27–31, 2026 · 15 students, 2 teachers
Everything below is provided by the City. It must be set up and tested before teacher training. The room and setup complete by Tuesday evening, July 21, MetAiBlock runs a dry run that same evening, and every machine is verified during training (July 22 to 24).
The City provides all laptops through Parks & Recreation (not city IT). 17 total: 15 students plus 2 teachers. Nothing heavy is needed. An i5-class processor is ideal, and 8 to 16 GB of RAM is fine. Each machine needs a working mic, speakers, and camera.
| Item | Qty / detail | Needed by | Owner | Status |
|---|---|---|---|---|
| Student laptops | 15 (one per student). i5-class processor ideal, 8 to 16 GB RAM is fine. | Jul 22 | City (Parks & Rec) | ☐ |
| Teacher laptops | 2 (one per teacher). Same specs as student machines. | Jul 21 | City (Parks & Rec) | ☐ |
| Backup laptops | 2 to 3 spares on hand, in case a machine fails (dead battery, bad keys). MetAiBlock requested this. | Jul 22 | City (Parks & Rec) | ☐ |
| Working microphone | One working mic per machine. Students record and capture audio for their projects. | Jul 22 | City | ☐ |
| Working speakers / audio output | Working sound on every machine (students play and review music). | Jul 22 | City | ☐ |
| Working camera | A working camera on every machine. | Jul 22 | City | ☐ |
| Current web browser | Chrome, updated to current version, on every machine. | Jul 22 | City IT | ☐ |
| Headphones (nice to have) | Not required. Helpful for the music work, so kids are not all playing different audio at once. City is checking what it can provide. We can work around it. | If available | City | ☐ |
⚠️ Critical: remove the laptops from the city domain / GPO
The single biggest access dependency. City IT must handle this before training.
The City sets the room up classroom-style with a projector. Teachers project for the group and interactive moments, and most work happens on individual laptops. No 15 wired ports are needed.
| Item | Qty / detail | Needed by | Owner | Status |
|---|---|---|---|---|
| Projector or large screen | 1, set up classroom-style. Must connect to a teacher laptop (HDMI or an adapter). | Jul 21 | City | ☐ |
| Backup portable projector | 1 spare on hand, ready in case the connectors do not work with the laptops. | Jul 21 | City | ☐ |
| HDMI cable / adapter | 1 (plus an adapter if the screen needs one). Reaches the teacher station. | Jul 21 | City | ☐ |
| Room speakers | 1 set, loud enough to fill the room. Plays songs and videos for the group. | Jul 21 | City | ☐ |
Every activity runs online. The network must carry all 17 devices at once doing heavy AI use, media generation, and downloads. This is the biggest technical risk, so the City runs a live stress test before training.
| Item | Qty / detail | Needed by | Owner | Status |
|---|---|---|---|---|
| Stable WiFi for all 17 devices | Comfortably supports all 17 devices at once, doing heavy AI use, media generation, and large uploads and downloads. | Jul 21 | City IT | ☐ |
| Live stress test | City runs a live test on Wednesday: all 15 student laptops doing something at once, to watch for slowdown or glitching. | Jul 22 | City IT | ☐ |
| Network / login for camp devices | Wi-Fi name and password (or wired access) provided for all program machines. | Jul 21 | City IT | ☐ |
| Backup hotspot / data line | A contingency ready in case the main network struggles under load. City decides after the Wednesday test whether a dedicated data line is needed. | Contingency | City IT | ☐ |
This is the make-or-break section. The laptops can be perfect, but if the network blocks these sites or sign-ins, the camp cannot run. City IT will whitelist the domains below and send the list to their security team.
⚠️ Make-or-break: get every item below confirmed by IT
If any one of these is blocked, that activity stops for the whole class.
Three dates drive everything. Each requirement above ties back to these.
City Parks & Recreation provides and confirms the laptops (17 total, plus 2 to 3 backups). City IT handles the domain / GPO removal, the domain whitelist, the network, and the on-site support window.
MetAiBlock runs a dry run on Tuesday evening (July 21) and tests every machine during teacher training (July 22 to 24), so any gap is caught before Day 1, not during it.
Please confirm City IT can approve the domain / GPO removal, the domain whitelist (sent to the security team), the sign-in policy, and live on-site support Wednesday to Friday, about 10am to 3pm.